NEW QUESTION # 86
The project team is working to reduce the building's total energy costs in a cold climate. Which is the best strategy for the project team to consider?
- A. Highly reflective roof
- B. Additional envelope insulation
- C. Window shades
- D. Increased cooling efficiency
Answer: B
Explanation:
Detailed
In a cold climate, additional envelope insulation is the most effective strategy for reducing energy costs. Improved insulation minimizes heat loss through the building envelope, reducing the demand for heating systems. This aligns with LEED's focus on enhancing energy efficiency and thermal performance in building design.
NEW QUESTION # 87
A LEED Building Design and Construction project includes an outdoor stage for theatrical performances. In pursuit of Sustainable Sites Credit, Light Pollution Reduction the engineer has specified an LED fixture to illuminate actors on the stage while limiting light pollution. Which of the following suggestions should the LEED AP give to the project owner?
- A. Compare the energy consumption against an alternative
- B. Calculate the return on investment over the 20-year life of the project
- C. Modify the design to enclose the performance areas
- D. Inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction
Answer: D
Explanation:
The Sustainable Sites Credit, Light Pollution Reduction aims to minimize the adverse effects of artificial lighting on the night sky, human health, and wildlife1. However, the credit does not apply to lighting that is required for safety, security, or emergency purposes2. According to the LEED Reference Guide for Building Design and Construction, lighting for theatrical performances is considered an emergency purpose and is exempt from the credit requirements3. Therefore, the LEED AP should inform the owner that the LED fixture is exempt from Sustainable Sites Credit, Light Pollution Reduction and does not need to be modified or compared to an alternative. Enclosing the performance areas would not reduce light pollution, but rather increase energy consumption and affect the outdoor experience. Calculating the return on investment over the
20-year life of the project is irrelevant to the credit and would not help achieve it.
NEW QUESTION # 88
Innovation credits for exemplary performance can be awarded for
- A. achieving double the credit requirements
- B. achieving one pilot credit
- C. demonstrating a qualitative improvement in environmental performance
- D. demonstrating significant environmental benefits
Answer: A
Explanation:
Exemplary performance credits are one of the options to earn innovation points under the LEED v4.1 rating system. They are typically awarded for achieving double the credit requirements or the next incremental percentage threshold of an existing LEED v4.1 prerequisite or credit that allows exemplary performance. For example, to earn an exemplary performance point for the Energy and Atmosphere credit Optimize Energy Performance, the project must demonstrate a percentage improvement in the proposed building performance rating compared to the baseline building performance rating per ASHRAE 90.1-2010 by at least 12 percentage points for new construction, or by at least 16 percentage points for major renovations.
References: = NC-v4.1 INc1: Innovation | LEEDuser, Guide to Exemplary Performance Credits in LEED-NC v4 | LEEDuser
NEW QUESTION # 89
Which individual occupant lighting control meets the requirements of Indoor Environmental Quality Credit, Interior Lighting?
- A. Three Level (on, 50%, off)
- B. Three Level (on, 75%, off)
- C. Three Level (on, 25%, off)
- D. Two Level (on, off)
Answer: C
Explanation:
The Indoor Environmental Quality Credit, Interior Lighting, requires the project team to provide individual occupant lighting control for at least 90% of the individual occupant spaces, or at least 50% of the shared multi-occupant spaces. The lighting control must enable occupants to adjust the lighting to suit their individual tasks and preferences, and must have at least three lighting levels, excluding off1. Therefore, a three level (on, 25%, off) lighting control meets the requirements of this credit, while a two level (on, off) lighting control does not. A three level (on, 50%, off) or a three level (on, 75%, off) lighting control may also meet the requirements, depending on the lighting power density and the daylight availability in the space2.
Reference:
* LEED v4 Reference Guide for Building Design and Construction, Indoor Environmental Quality Credit: Interior Lighting, page 7071
* Interior lighting | U.S. Green Building Council3
NEW QUESTION # 90
Which site preparation and construction method contributes to earning the Materials and Resources Credit, Construction and Demolition Waste Management?
- A. Implement in situ soil remediation and post removal of the existing concrete pavement
- B. Salvage and recycle 50% of the existing materials (based on volume) generated during site demolition for three material streams
- C. Reuse excavated soil and land-clearing debris
- D. Ensure reduction of pollution from construction activities by using airborne dust generation capture systems
Answer: B
Explanation:
The Materials and Resources Credit, Construction and Demolition Waste Management aims to reduce the amount of construction and demolition waste disposed of in landfills and incineration facilities by recovering, reusing, and recycling materials. According to the LEED v4 Reference Guide for Building Design and Construction, one of the options to achieve this credit is to divert at least 50% of the total construction and demolition material from disposal and recycle or salvage at least three material streams1. Therefore, salvaging and recycling 50% of the existing materials (based on volume) generated during site demolition for three material streams would contribute to earning this credit. The other options are not related to this credit, but to other credits or prerequisites, such as Sustainable Sites Prerequisite: Construction Activity Pollution Prevention1, Materials and Resources Prerequisite: Storage and Collection of Recyclables1, and Materials and Resources Credit: Building Product Disclosure and Optimization - Sourcing of Raw Materials1.
Reference:
* LEED v4 Reference Guide for Building Design and Construction, Materials and Resources Credit: Construction and Demolition Waste Management, page 5481
* LEED v4 Construction and Demolition Waste
NEW QUESTION # 91
Which of the following buildings meets the Minimum Program Requirements for LEED certification?
- A. A 2,500 ft2 (232 m2) mobile Health Clinic located on a previously constructed above-water dock
- B. A 20,000 ft2 (1 859 m2) Transit Parking Garage located on a previously developed five-acre site
- C. A 5,000 ft2 (465 m2) Science Education center on an above-water pier that is being built specifically for the Education center
- D. A 1,500 ft2 (139 m2) Tourism Center located on a previously undeveloped one-acre site
Answer: C
Explanation:
The Minimum Program Requirements (MPRs) for LEED certification are:
* MPR 1: Must be in a permanent location on existing land
* MPR 2: Must use reasonable LEED boundaries
* MPR 3: Must comply with project size requirements
Option A does not meet MPR 1 because it is located on a previously undeveloped site, which is not considered existing land. Option B does not meet MPR 3 because it is a parking garage, which is excluded from LEED certification unless it is part of a larger project. Option C does not meet MPR 1 because it is a mobile clinic, which is not considered permanent. Option D meets all the MPRs because it is a permanent building on existing land, it has reasonable LEED boundaries, and it meets the minimum gross floor area of
1,000 ft2 (93 m2) for BD+C projects.
References:
* LEED minimum program requirements
* Minimum Program Requirements (MPRs)
* What do the LEED Minimum Program Requirements Really Mean?
NEW QUESTION # 92
Sustainable Sites Credit, Site Assessment requires evaluation of
- A. vegetation, topography, archaeology
- B. human health effects, climate, land value
- C. soils, archeology, hydrology
- D. topography, hydrology, human use
Answer: D
Explanation:
The Sustainable Sites Credit, Site Assessment requires the project to conduct and document a site inventory and analysis that evaluates the existing conditions and features of the site, such as topography, hydrology, human use, climate, vegetation, soils, and human health effects1. The purpose of the site assessment is to inform the design and development of the site in a way that protects, restores, and enhances the environmental quality and performance of the site1. The site assessment should include the following elements:
Topography: The shape and elevation of the land surface, including slopes, drainage patterns, and erosion potential.
Hydrology: The movement, distribution, and quality of water on the site, including surface water, groundwater, precipitation, and runoff.
Human use: The current and planned use of the site and its surroundings, including zoning, land use, transportation, utilities, and cultural resources.
Climate: The long-term weather patterns and conditions of the site, including temperature, humidity, wind, solar radiation, and precipitation.
Vegetation: The types, distribution, and condition of plants on the site, including native, invasive, and endangered species, and their ecological functions and values.
Soils: The physical, chemical, and biological properties of the soil on the site, including texture, structure, organic matter, pH, fertility, and contamination.
Human health effects: The potential impacts of the site conditions and features on the health and well-being of the occupants and the surrounding community, such as noise, air quality, water quality, and exposure to hazardous substances.
Reference:
LEED Reference Guide for Building Design and Construction v4
Sustainable Sites Credit, Site Assessment
Site Assessment - SITES
Site Assessment and Analysis - Whole Building Design Guide
NEW QUESTION # 93
The current facilities requirements (CFR) and operations and maintenance plan (OMP) required for Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification must include
- A. minimum outside air requirements
- B. issue logs
- C. functional performance tests
- D. installation verification (construction) checklists
Answer: A
Explanation:
The current facilities requirements (CFR) and operations and maintenance plan (OMP) are two documents that are required for the Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification.
The CFR is a document that describes the owner's project requirements, such as the design intent, performance goals, and operational needs of the building. The OMP is a document that provides information and guidance on how to operate and maintain the commissioned systems and equipment. According to the LEED v4 Reference Guide for Building Design and Construction, the CFR and OMP must include the minimum outside air requirements, which are the minimum rates of outdoor air ventilation that are needed to provide acceptable indoor air quality and thermal comfort for the occupants1. The issue logs, functional performance tests, and installation verification (construction) checklists are not required to be included in the CFR and OMP, but they are part of the commissioning process and documentation.
References:
*LEED v4 Reference Guide for Building Design and Construction, Energy and Atmosphere Prerequisite:
Fundamental Commissioning and Verification, page 2611
*Fundamental commissioning and verification | U.S. Green Building Council2
NEW QUESTION # 94
Which strategy should be employed to improve daylighting when designing a new building?
- A. Increase the building depth
- B. Decrease the number of exterior light shelves
- C. Increase the number of skylights
- D. Increase the height of interior partitions
Answer: C
Explanation:
Increase the number of skylights
Skylights are openings in the roof or ceiling that allow natural light to enter the building. They can improve daylighting by providing more uniform and diffuse illumination, reducing the need for artificial lighting, and enhancing the visual comfort and well-being of occupants. Skylights can also reduce cooling loads by minimizing solar heat gain through the roof. However, skylights must be designed carefully to avoid glare, overheating, and heat loss issues.
NEW QUESTION # 95
A mixed-use development is located 1/2 mi. (0.80 km) from a future commuter rail line station.Which of the following pieces of information is needed when determining whether the rail line station can contribute to Location and Transportation Credit, Access to Quality Transit?
- A. Discounted rail pass availability
- B. Rail line station construction completion date
- C. Passenger capacity
- D. Connections to transfer routes
Answer: B
Explanation:
Explanation
The rail line station construction completion date is needed when determining whether the rail line station can contribute to Location and Transportation Credit, Access to Quality Transit. This is because the credit requires that the transit service must be existing or planned to be in operation within two years of the project's occupancy1. Discounted rail pass availability, connections to transfer routes, and passenger capacity are not relevant for this credit1.
References:
*Access to quality transit, p. 1
NEW QUESTION # 96
An HVAC system consists of an air handler supplying conditioned air (mixture of return air andoutdoor air) to anoffice, corridor, conference room and lobby. For Indoor Environmental Quality Prerequisite, Minimum Indoor AirQuality Performance, the ventilation rate procedure calculations must be based upon what HVAC systemconfiguration?
- A. Multiple-zone system
- B. 100% outdoor air system
- C. Single-zone system
- D. Mixed-mode system
Answer: A
Explanation:
Explanation
A multiple-zone system is a system that has one or more air handlers supplying conditioned air to more than one zone. A zone is a space or group of spaces within a building with heating and cooling requirements that are sufficiently similar so that desired conditions (e.g., temperature) can be maintained throughout using a single controlling device. The ventilation rate procedure calculations must be based on the multiple-zone system configuration because the HVAC system in the question serves different zones with different ventilation requirements.References: LEED v4 Reference Guide for Building Design and Construction, p.6881; ASHRAE Standard 62.1-2010, Section 6.2.52
NEW QUESTION # 97
Increasing which of the following variables will require an increase in the outdoor airflow rate under Indoor Environmental Quality Prerequisite, Minimum Indoor Air Quality Performance?
- A. Number of occupants
- B. System ventilation efficiency
- C. Supply air temperature set point
- D. Supply air velocity
Answer: A
Explanation:
The outdoor airflow rate is the amount of outdoor air that is supplied to the building by the ventilation system to dilute indoor air pollutants and provide fresh air for the occupants. The outdoor airflow rate depends on the ventilation standard that the project follows, which can be either ASHRAE 62.1-2010 or CEN Standard EN 15251-20071. Both standards specify the minimum outdoor airflow rate per person and per unit area for different occupancy types and zones. Therefore, increasing the number of occupants will require an increase in the outdoor airflow rate to maintain the minimum ventilation level. The other variables, such as supply air velocity, system ventilation efficiency, and supply air temperature set point, do not directly affect the outdoor airflow rate, although they may influence the energy consumption and thermal comfort of the ventilation system.
Reference:
LEED Reference Guide for Building Design and Construction v4
Minimum Indoor Air Quality Performance
Ventilation for Acceptable Indoor Air Quality - ASHRAE
Indoor environmental input parameters for design and assessment of ... - CEN
NEW QUESTION # 98
The design team is attempting to achieve the Increased Ventilation strategy in the Indoor Environmental Quality Credit, Enhanced Indoor Air Quality in a conference room. The associated ASHRAE standard requires 400 CFM (11.3 CMM) of ventilation air, but the local code requires 500 CFM (14.1 CMM) of ventilation air. What is the required minimum amount of ventilation air to achieve this credit?
- A. 520 CFM (14.7 CMM)
- B. 500 CFM (14.1 CMM)
- C. 650 CFM (18.4 CMM)
- D. 400 CFM (11.3 CMM)
Answer: B
Explanation:
Detailed
The project must meet the more stringent requirement, which in this case is 500 CFM (14.1 CMM) as per the local code. LEED Enhanced Indoor Air Quality prerequisites and credits prioritize compliance with the highest applicable ventilation standards to improve indoor air quality and occupant comfort.
NEW QUESTION # 99
Which of the following standards needs to be followed to comply with Indoor Environmental Quality Credit, Thermal Comfort?
- A. ASHRAE 62.1-2010
- B. ASHRAE 55-2010
- C. ASHRAE 189.1-2010
- D. ASHRAE 90.1-2010
Answer: B
Explanation:
Explanation
To comply with Indoor Environmental Quality Credit, Thermal Comfort, the standard that needs to be followed is ASHRAE 55-2010, Thermal Environmental Conditions for Human Occupancy, with errata or a local equivalent1. This standard specifies the combinations of indoor thermal environmental factors and personal factors that will produce thermal environmental conditions acceptable to a majority of the occupants within the space2. The standard also provides methods for measuring and evaluating thermal comfort, as well as guidance for design, operation, and maintenance of thermal comfort systems2. References: Thermal comfort; ASHRAE 55-2010
NEW QUESTION # 100
Which of the following sinks is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction?
- A. A sink in a hotel room bathroom
- B. A sink in a shared office restroom
- C. A sink in a school classroom
- D. A sink in an office restroom
Answer: A
Explanation:
A sink in a hotel room bathroom is classified as a private lavatory faucet under Water Efficiency Credit, Indoor Water Use Reduction. According to the LEED v4 BD+C Reference Guide, a private lavatory faucet is defined as "a faucet that is not generally accessible and is used only by the building's occupants and not by the public or visitors" 1. A sink in an office restroom, a school classroom, or a shared office restroom are examples of public lavatory faucets, which have different baseline flow rates and requirements.
Reference: LEED v4 BD+C Reference Guide, Water Efficiency Category, WEc Indoor Water Use Reduction, page 681.
NEW QUESTION # 101
A project in a cold climate does not want a highly reflective roof because they want the heat absorption. How can this project comply with Sustainable Sites Credit, Heat Island Reduction?
- A. The credit can only be achieved by using an alternative compliance path
- B. The credit is not feasible for this project
- C. The credit is applicable for projects that document this special condition
- D. The credit may be achieved by using nonroof measures only
Answer: D
Explanation:
Explanation
The credit may be achieved by using nonroof measures only, such as shading, paving, and vegetation, to reduce the heat island effect on the site. The credit does not require a highly reflective roof for all projects, but allows for flexibility and trade-offs depending on the climate and design conditions. The project can use the Heat Island Reduction 1 to demonstrate compliance with the credit requirements. The credit is feasible and applicable for this project, and does not need an alternative compliance path. References: SS Credit Heat Island Reduction, LEED v4 Reference Guide for Building Design and Construction234
NEW QUESTION # 102
A project will renovate a building with historic designation into new office space. The surface area of the existing building structure and envelope is 100,000 ft² (9,290 m²). How much of the existing building will need to be reused to earn 5 points for the Materials and Resource Credit, Building Life-Cycle Impact Reduction?
- A. There is no minimum
- B. 80,000 ft² (7,432 m²)
- C. 90,000 ft² (8,361 m²)
- D. At least 50% of the surface area
Answer: D
Explanation:
Detailed Explanation:
To earn 5 points under the Materials and Resources (MR) Credit for Building Life-Cycle Impact Reduction, at least 50% of the surface area of the existing building structure and envelope must be reused. This strategy preserves the embodied energy in the building materials, reducing the environmental impact of new material extraction, processing, and transportation, which is a core focus of LEED's sustainable building strategies.
NEW QUESTION # 103
Which group of chemicals emitted by some building materials is linked to asthma, chronic obstructive pulmonary disease, and cancer?
- A. Volatile Organic Compounds (VOCs)
- B. Polyvinyl Chlorides (PVCs)
- C. Nitrogen Oxides (NOx)
- D. Chlorofluorocarbons (CFCs)
Answer: A
Explanation:
Volatile Organic Compounds (VOCs) (D) are chemicals often found in building materials, such as paints, adhesives, and finishes, and are associated with health risks, including asthma, chronic obstructive pulmonary disease, and certain cancers. VOCs release harmful gases that contribute to indoor air pollution, and LEED encourages using low-VOC materials to protect occupant health. PVCs (B) and CFCs (C) are harmful to the environment but are not directly linked to these health conditions.
NEW QUESTION # 104
A new five-story building with a 30,000 ft2 (2 800 m2) footprint is being designed on a previously disturbed100,000 ft2 (9 290 m2) site. The remaining on-grade surface will be 35,000 ft2 (3 250 m2) of asphalt parking, and 35,000 ft2 (3 250 m2) of native vegetated open space. To achieve a point for exemplary performance under Option 1 of Sustainable Sites Credit, Site Development - Protect or Restore Habitat, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of
- A. 25,000 ft2 (2 300 m2)
- B. 12,500 ft2 (1 160 m2)
- C. 35,000 ft2 (3 250 m2)
- D. 15,000 ft2 (1 400 m2)
Answer: A
Explanation:
According to the LEED v4 Reference Guide for Building Design and Construction, Option 1 of the Site Development - Protect or Restore Habitat credit requires restoring 25% of the site area (including the building footprint) with native or adapted vegetation1. To achieve exemplary performance, the project must double the credit requirements and restore 50% of the site area2. In this case, the site area is 100,000 ft2 (9 290 m2), so the project must restore 50,000 ft2 (4 645 m2) with vegetation. The project already has 35,000 ft2 (3 250 m2) of native vegetated open space, so it needs to add another 15,000 ft2 (1 395 m2) of vegetation. Since the on- grade surface is fully occupied by the building footprint and the asphalt parking, the only option is to incorporate a vegetated roof. Therefore, the design team will have to incorporate a native and/or adapted vegetated roof with a minimum area of 15,000 ft2 (1 395 m2). References: SS Credit Site Development - Protect or Restore Habitat, LEED v4 Reference Guide for Building Design and Construction13
NEW QUESTION # 105
Which of the following innovation proposals is most likely to be successful to achieve an Innovation Credit?
- A. Providing an educational program on the environmental and human health benefits of green building practices
- B. Distributing leaflets to project occupants about available public transit services nearby
- C. Being located next to a 20 mi. (32 km) award-winning bicycle trail
- D. Including locked, indoor bicycle storage for 100% of project occupants
Answer: A
Explanation:
Explanation
Providing an educational program on the environmental and human health benefits of green building practices is a potential innovation strategy that is not addressed by any existing LEED credit. It also meets the criteria of being measurable, replicable, and having a positive impact on the project and the environment.References:
LEED v4 BD+C Reference Guide, Innovation Category, INc1: Innovation, Option 1. Innovation (1 point), page 704.
NEW QUESTION # 106
The material cost for a project is $100,000. What is the minimum material value needed to achieve Materials and Resources Credit, Building Disclosure and Optimization, Sourcing of Raw Materials, Option 2.
Leadership Extraction
Practices?
- A. $22,500
- B. $25,000
- C. $12,500
- D. $10,000
Answer: B
Explanation:
According to the LEED v4 Reference Guide for Building Design and Construction, Option 2 of the Sourcing of Raw Materials credit requires using products that meet at least one of the responsible extraction criteria for at least 25%, by cost, of the total value of permanently installed building products in the project1. Therefore, for a project with a material cost of $100,000, the minimum material value needed to achieve this option is
25% of $100,000, which is $25,000.
NEW QUESTION # 107
Which item is included in the reuse calculation for Materials and Resources Credit, Building Life-Cycle Impact Reduction?
- A. Floor decking
- B. Plumbing fixtures
- C. Asbestos insulation
- D. Exterior glazing
Answer: A
Explanation:
Explanation
The reuse calculation for MR Credit Building Life-Cycle Impact Reduction includes the surface area of structural elements that are reused in place or salvaged and reinstalled, such as floor decking, columns, beams, and roof decking. Exterior glazing and plumbing fixtures are not considered structural elements and are not included in the reuse calculation. Asbestos insulation is a hazardous material that should be removed and disposed of properly, not reused. References: MR Credit Building Life-Cycle Impact Reduction, LEED v4 Reference Guide for Building Design and Construction123
NEW QUESTION # 108
Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space?
- A. Hospitality
- B. Core and Shell Development
- C. New Construction
- D. Retail
Answer: C
Explanation:
Explanation
New Construction is the appropriate rating system for a new mixed-use building with 300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail space. According to the LEED rating system selection guidance1, the New Construction rating system applies to buildings that are being newly constructed or going through a major renovation, and that include any of the following use types:
office, retail, hospitality, education, residential, warehouse and distribution centers, or data centers2. The New Construction rating system can also be used for mixed-use buildings that have more than one use type3. Since the project involves new construction of a mixed-use building with residential, hospitality, and retail uses, the New Construction rating system is the most suitable option. The other rating systems are not applicable because they are either specific to one use type (Retail and Hospitality) or to buildings that are not complete at the time of certification (Core and Shell Development).
LEED rating system selection guidance | U.S. Green Building Council
LEED v4: Building Design + Construction Guide - U.S. Green Building Council LEED v4 Rating Systems | USGBC-LI
NEW QUESTION # 109
......
USGBC LEED-AP-BD-C Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
Free USGBC LEED LEED-AP-BD-C Exam Question: https://itcertspass.itcertmagic.com/USGBC/real-LEED-AP-BD-C-exam-prep-dumps.html