NEW QUESTION # 81
Preventive Maintenance is defined as: Maintenance tasks, including inspection, service and or replacement, conducted at regular, scheduled intervals of calendar or operating time established to avoid failure based on average statistical anticipated lifetime.
There are cautions regarding the application of PM: No more than "A" percent of total failures are time based, wear out, in nature. .... thus. PM is an ineffective avoidance action for about *'B" percent of probable failures.

  • A. A = 40; B = 60
  • B. A = 20; B = 80
  • C. A = 60; B = 40
  • D. A = 80; B = 20

Answer: D


NEW QUESTION # 82
Work done to restore the function of an asset after failure or when failure is imminent.

  • A. Corrective Work
  • B. Rework
  • C. Quality Rate
  • D. Corrective Maintenance Hours Formula

Answer: A


NEW QUESTION # 83
the percentage of total maintenance labor hours used to restore equipment to a functional state after a failure or when failure is imminent

  • A. TOTAL MAINTENANCE TRAINING COST
  • B. Preventive Maintenance Cost Formula
  • C. Corrective Maintenance Hours
  • D. Condition Based Maintenance Cost

Answer: C


NEW QUESTION # 84
When forming teams to address reliability issues, four stages of team development should be recognized and managed by the reliability professional In the Performing stage, team members should not:

  • A. Swing from optimism to uncertainty.
  • B. Complete problem analysis.
  • C. Make changes to the process.
  • D. Begin to improve and control

Answer: A


NEW QUESTION # 85
For a reliability engineer, identify the appropriate key performance indicator below that he/she should receive (Leβ€ž that they can best influence or control and are accountable for):

  • A. Equipment utilization rate.
  • B. Mean Time Between Failures (MTBF).
  • C. Shift stream factor and production rate.
  • D. % rework (perform the same work on a piece of equipment in a short interval).

Answer: D


NEW QUESTION # 86
Total Available Time - (Idle Time + Downtime)

  • A. Equipment Availability Formula
  • B. Maintenance Unit Cost Formula
  • C. Uptime Formula
  • D. Ratio of Replacement Asset Value (RAV) to Craft-Wage Headcount Formula

Answer: C


NEW QUESTION # 87
The maintenance function should be viewed in value added terms and should be associated with profit and the optimization of maintenance costs. When developing the maintenance budget, it is important to:

  • A. Base the budget on the individual needs of each specific equipment item annually.
  • B. Determine, through benchmarking, the percentage of money spent on maintenance compared to the Replacement Asset Value of equipment.
  • C. Increase last year's budget by approximately 9.5% to 12% and be prepared to reduce the budgeted amount after management reviews the budget.
  • D. Review the budget from the previous year and increase the budget for the upcoming year based on the effects of inflation.

Answer: A


NEW QUESTION # 88
Percent overtime maintenance labor hours is:

  • A. Total overtime labor hours, divided by the total scheduled maintenance labor hours, expressed as a percentage.
  • B. Scheduled overtime maintenance labor hours used to maintain assets, divided by scheduled maintenance labor hours to maintain assets, expressed as a percentage.
  • C. Total overtime labor hours, divided by the total maintenance labor hours to maintain assets, expressed as a percentage.
  • D. Overtime maintenance labor hours used to maintain assets, divided by the total maintenance labor hours to maintain assets, expressed as a percentage.

Answer: D


NEW QUESTION # 89
All personnel, salaried and hourly, direct and indirect, who are responsible for executing work assignments pertaining to the maintenance of physical assets and components

  • A. Mean Time to Failure (MTTF)
  • B. INTERNAL MAINTENANCE EMPLOYEES
  • C. Total Maintenance Cost As a Percent of Replacement Asset Value (RAV)
  • D. Maintenance Training Hours

Answer: B


NEW QUESTION # 90
Which of the following is a disadvantage of the FIFO system?

  • A. Current revenues are distinct from older costs.
  • B. It is more difficult to manipulate.
  • C. Ending inventory is significantly different than current replacement cost.
  • D. It cannot be compared with the matching of cost flow and physical flow by the specific identification system.

Answer: B

Explanation:
One disadvantage of the first-in, first-out (FIFO) system is that it is more difficult to manipulate. That is, because the order in which products enter and leave inventory is predetermined, the business cannot structure imports and exports to increase or decrease inventory levels. Another problem with the FIFO system is that current revenues are matched with older costs, which can create confusion. Also, ending inventory will be roughly the same as current replacement cost, though this is an advantage of the FIFO system. Finally, the specific identification system's method of matching cost flow and physical flow is very similar to the FIFO system.


NEW QUESTION # 91
Total quality management focuses all employees on producing products that meet customer needs. This is done by:

  • A. Sharing information with all levels in the organization
  • B. Eliminating processes that waste time and materials
  • C. Balancing the needs of all stakeholders in the organization
  • D. Developing a high level of expertise in all employees

Answer: D


NEW QUESTION # 92
A large manufacturing company installed some asset monitoring device large motors that were deemed critical equipment. The monitoring devices engineering with vibration data, acoustic data, as well as operational performance data. What asset management strategy has the company selected for the

  • A. OBM (Operational Based Maintenance/CM (Corrective Maintenance)
  • B. PM (Preventive Maintenance/OBM Operator Based Maintenance)
  • C. CBM (Condition Based Maintenance/CM (Corrective Maintenance)
  • D. CBM (Conditioned Based Maintenance)/PDM (Predictive Maintenance)

Answer: D


NEW QUESTION # 93
Metrics that describe the Reliability, Availability and Maintainability (RAM) characteristics of a component, asset or even facility β†’ Leading Indicator

  • A. False
  • B. True

Answer: A


NEW QUESTION # 94
Which inventory system requires regular physical inventory counts?

  • A. Periodic
  • B. Neither periodic nor perpetual
  • C. Both periodic and perpetual
  • D. Perpetual

Answer: C

Explanation:
Both the periodic and the perpetual inventory systems require regular physical inventory counts. In the periodic inventory system, the physical count occurs at the end of the accounting period. It is necessary for the calculation of cost of goods sold and the matching of physical count to inventory balance. The perpetual inventory system requires a physical count to identify inaccuracies in the perpetual records.
Employee theft and shoplifting can result in inventory inaccuracies.


NEW QUESTION # 95
The number of units produced during a designated time period.

  • A. Standard Units Produced
  • B. Total Units Produced
  • C. Availability Formula
  • D. TOTAL INTERNAL MAINTENANCE EMPLOYEE LABOR COSTS

Answer: B


NEW QUESTION # 96
Time when the asset is scheduled to run divided by total available time expressed as a percentage.

  • A. UTILIZATION TIME
  • B. Performance Efficiency
  • C. Quality
  • D. Preventive Maintenance Cost

Answer: A


NEW QUESTION # 97
Why may two different materials, both with the same surface temperature, appear to havedifferent temperatures when viewed with a thermal imager?

  • A. They have different thermal capacities.
  • B. They have different convective coefficients.
  • C. They have different emissivities.
  • D. They have different conductivities.

Answer: C


NEW QUESTION # 98
measure of the variables inherent in the design that affect availability. In the calculation of downtime, it usually includes only active repair time. It does not include preventive maintenance time and administrative or logistic delays, but does include corrective maintenance downtime β†’ Maintenance Action

  • A. False
  • B. True

Answer: A


NEW QUESTION # 99
This metric is the ratio of the benefit to the cost of training internal maintenance employees.

  • A. Maintenance Training Return on Investment (ROI)
  • B. Maintenance Training ROI Formula
  • C. Maintenance cost will decrease as reliability increases. (T/F)
  • D. Condition Based Maintenance Cost

Answer: A


NEW QUESTION # 100
Maintainability is defined as:

  • A. a characteristic that pertains to the efficient conversion of labor, raw material and energy into an on-specification product where the ratio of output to input is optimal
  • B. a characteristic of a system or product design .that pertains to the ease, accuracy, safety and economy in the performance of maintenance functions ^
  • C. the probability that an item will carry out its stated function adequately for the time intervalwhen operating according to the design function
  • D. a characteristic that pertains to the amount of time the machinery/equipment will be available when needed

Answer: B


NEW QUESTION # 101
......